Umm Al Quwain Coastal Road Thermoplastic Marking
Re-mark 6.8 km of the UAQ coastal road with humidity-resistant thermoplastic, edge lines and pedestrian crossings. The existing cold-paint lines had degraded within 14 months due to coastal salt spray and humidity, and the client needed a longer-life system.
The Challenge
Re-mark 6.8 km of the UAQ coastal road with humidity-resistant thermoplastic, edge lines and pedestrian crossings. The existing cold-paint lines had degraded within 14 months due to coastal salt spray and humidity, and the client needed a longer-life system.
Our Solution
Specified a 3.5 mm hot-applied thermoplastic system with hydrocarbon resin modified for coastal-humidity resistance. Anti-skid aggregate was applied on 8 pedestrian crossings, with Type II glass beads on edge lines for night delineation along the dark coastal stretch.
Execution
Crews water-blasted ghost lines and salt contamination, then applied thermoplastic at 185°C. A total of 27 km of line was applied across 6.8 km of coastal road, with anti-skid surface on 8 raised pedestrian crossings and preformed thermoplastic hazard symbols on 12 coastal-curve sections.
Project Gallery
Related projects
Abu Dhabi–Al Ain Highway Thermoplastic Marking
Re-mark 42 km of a high-speed inter-city highway with minimal lane closures during peak pilgrimage and commuter traffic, while upgrading reflectivity to night-driving standards.
Dubai Sheikh Zayed Road Thermoplastic Re-Marking
Re-mark 14 km of Dubai's flagship Sheikh Zayed Road corridor across 6 lanes plus hard shoulder, upgrading reflectivity to RTA night-driving spec while keeping the highway open during daytime peak traffic. The existing lines had degraded after 5 years of heavy HGV and commuter traffic.
Ras Al Khaimah Quarry Access Road Thermoplastic Marking
Re-mark 8.6 km of single-carriageway access road serving three RAK limestone quarries, with heavy HGV traffic, dust accumulation and steep gradients. The existing lines had been abraded by quarry-truck traffic within 18 months and the client needed a longer-life solution.
Start your marking project today
Choose the channel that suits you. Our specialists respond within 1 business hour during working days.
Why Gulf Seismic?
- ✓ 10+ years delivering marking projects in the Gulf
- ✓ ISO 9001 certified, RTA & MOMRA compliant
- ✓ ICAO Annex 14 trained aviation crews
- ✓ 850+ projects across 16 cities