Sharjah Hamriyah Free Zone Industrial Hazard Marking
Mark hazardous zones, pipe identification and emergency escape routes across a live petrochemical facility in Hamriyah Free Zone Zone 1, with hydrocarbon exposure and ATEX Zone 1 requirements. The facility had to remain operational throughout, with marking applied in classified areas only during permit-controlled shutdowns.
The Challenge
Mark hazardous zones, pipe identification and emergency escape routes across a live petrochemical facility in Hamriyah Free Zone Zone 1, with hydrocarbon exposure and ATEX Zone 1 requirements. The facility had to remain operational throughout, with marking applied in classified areas only during permit-controlled shutdowns.
Our Solution
Applied novolac epoxy and polyurea systems rated for hydrocarbon exposure, with ASME A13.1 pipe banding on 12 km of pipework and photoluminescent emergency escape route marking. All work was sequenced around permit-to-work (PTW) windows, with ATEX-rated equipment used in classified zones.
Execution
Conducted chemical and substrate audit, ground and profiled surfaces to CSP-4, applied novolac epoxy in process zones and polyurea in traffic corridors. Pipe banding was installed on 12 km of pipework per ASME A13.1 colour code, and 2.1 km of photoluminescent escape route was applied with charging-verification testing.
Project Gallery
βWorking in ATEX Zone 1 requires discipline. Gulf Seismic's PTW management was exemplary β zero incidents across 6 weeks of complex marking.β
Related projects
Jubail Petrochemical Plant Hazard Marking
Mark hazardous zones, pipe identification and emergency escape routes across a live petrochemical plant with hydrocarbon exposure and ATEX requirements.
Sharjah Manufacturing Facility Epoxy Floor
Install a hygienic, chemical-resistant floor across a 4,500 mΒ² manufacturing facility with minimal production downtime and strict hygiene requirements.
Sharjah University City Road Marking
Re-mark 9.4 km of internal roads and pedestrian crossings across Sharjah's University City campus, with traffic-calming humps, raised pedestrian crossings and dedicated shuttle-bus lanes. The work had to be sequenced around the academic calendar with zero disruption during exam weeks.
Start your marking project today
Choose the channel that suits you. Our specialists respond within 1 business hour during working days.
Why Gulf Seismic?
- β 10+ years delivering marking projects in the Gulf
- β ISO 9001 certified, RTA & MOMRA compliant
- β ICAO Annex 14 trained aviation crews
- β 850+ projects across 16 cities